Airbus
Final Assembly Line China (FAL C), Tianjin
Infrastructure Facilities
 |
 |
production area Tianjin, planning
march 2007 |
|
Client:
Airbus Deutschland GmbH, Hamburg, Germany
Construction Costs:
not specified
Services:
basic evaluation, preliminary planning, concept design,
controlling performance during construction
Period:
2006 till expected 2009
|
|
Airbus Deutschland GmbH intends to produce the
Single Aisle Series Aircrafts of the type A320 in China, the first
delivery is arranged for 2009.
The Final Assembly Line for Aircrafts will include all necessary
production- and infrastructure facilities. It is located at a dedicated
construction site at the planned „Tianjin Airport Industrial
Park“. The construction site contains a useable area of 70
ha, which includes 60 ha for the production. All advanced production
hangars have to be equipped with several media supply and disposal
pipe lines. Furthermore high load vehicle roads, parking spaces,
taxiways and apron areas for the aircraft series of A320 have to
be implemented.
The construction of the production hangars and infrastructure measures
are scheduled within two years. The supply and disposal facilities
are designed for the requirements of final extension of the plant.
In addition to the design of operational surfaces and the infrastructure
facilities, the scope of work carried out by Sellhorn also contains
the cables and pipes for all media: 10/0.4 kV-electrical supply,
data- and safety systems, heating technology, cooling technology,
steam, condensate, compressed air, potable and process water, water
for fire fighting, sewage as well as storm water (collection and
discharge to the public sewer system).
The factory supply with primary energy and supply medias will be
provided by external suppliers. Therefore piping systems will be
connected with the public provider and deliver the media to the
so-called powerhouse. Inside of the powerhouse the medias will be
converted according to the requirements of production and distributed
to the several production facilities of the area.
The main piping ring with all several supply lines has a total length
of 2.6 kilometres. For the connection of the pipe lines to the deep
founded production buildings, special solutions were developed to
avoid damages due to the differences of settlement. A permanent
supply will be guaranteed due to the installed ring system with
two connection points to the powerhouse.
Storm water will flow of through ground pipes to the public system.
The connection to the public rain water pipe takes place at several,
already existing connection points along the whole north side of
the area.
The height situation of the existing sewage pipe requires a free
surface pipe system to the public main sewer. Connection manholes
are foreseen between the factory sewage network and public pipe.
Inside the connection manhole MID (magnetic inductive flow meter)
are installed to control the maximum waste load of the water.
Concrete, concrete blocks is designated for the surfacing of the
apron areas and the adjoining surface. The main road of the AIRBUS
area will be built in asphalt. The apron areas will be implemented
with a hydraulic bounded base layer. The other areas will be built
with aggregate base layers. A total of 26 hectare area will be paved.
|