Strengthening
of Ericus quay wall, Hamburg
 |
 |
Front view of the existing quay
wall |
|
Client:
HafenCity Hamburg GmbH, Hamburg
Construction Costs:
Approx. 5.0 mio. €
Services:
Study of Alternatives, Tender Documents, Execution Design,
Site Supervision
Period:
2007 - 2008
|
|
The Ericus quay wall is one of the most prominent
areas in the east of Hamburg’s new developed district HafenCity
with long historical background. In 1611 a bastion was erected at
the Ericus area as part of the town wall. In 1885 a first quay wall
was erected and since then the area was used for handling fuel products.
In 1907 the quay wall was heightened and over the years partly renovated
and modified.
From 2010 the publishing company SPIEGEL Group will move its head
office to the Ericus area, so the quay wall has to be strengthened.
To fulfil future requirements Sellhorn Inge¬nieurgesellschaft
was contracted to investigate possible strengthening alternatives.
Afterwards one alternative was taken into consideration for further
planning and detailed for tendering and execution design. After
the contract award Sellhorn provided the site supervision.
The
quay wall has a length of about 312 m und consists of a 5.75 m high
gravity wall (masonry and concrete) that is deep founded at wooden
piles. To clarify and affirm the exact geometry several excavations
were carried out during the strengthening study. A first static
recalculation of the structural system showed insufficient stability,
particularly due to the high design criteria for water pressure
according to the new standard.
After a reduction of loading and calculation with average values
of soil parameters the calculated stability could be satisfactorily
proved. Deformations of the quay wall, which already occurred and
still remain, and failure modes could be reconstructed with the
developed structural system.
Finally, the quay wall was strengthened by a new anchorage with
jet grouted piles (GEWI) and a waterside concrete waling. Due to
historical architectural reasons, beside concrete and masonry works
including crack restauration, dolphins and mooring hooks were installed.
From the beginning of the planning process several authorities and
others were involved, like monument protection authority, archaeologists,
structural safety engineers and the designer of the SPIEGEL Group.
|