Two
Fishery Harbours in Sri Lanka
 |
 |
|
|
Client:
Ministry of Fisheries/Sri Lanka
Construction Costs:
12 million US$
Service:
Feasibility study,
design, contracting, construction supervision
Period:
May 2004 May 2007
Cooperation:
NIRAS a/s (Denmark)
Lanka Hydraulic Institute
(Sri Lanka) |
|
As part of the Asia Development Bank financed Coastal
Resources Management Project (CRMP) the fishery infrastructure of Sri
Lanka shall be improved. This includes the construction of two fishery
harbours, namely Ambalangoda at the south-west coast and Hanbantota
at the south-east coast. The objectives are to provide at each side
sheltered area for the fishing boats, quay wall for fish landing and
supply of boats and a terminal area for harbour operation by private
entities.
A British consultant has developed harbour concepts which finally proved
to be not feasible (not economically viable due to excessive costs).
NIRAS Portconsult a/s (Denmark), Lanka Hydraulic Institute (Sri Lanka)
and Sellhorn Ingenieurgesellschaft, the group is the design consultant
for the coastal stabilisation component of the CRMP, have been entrusted
to review the concepts and cut the works to a feasible level considering
engineering sound civil designs and providing sufficient capacity within
the allocated project budget.
The nearshore wave climate has been reviewed at both sites and a criteria
for sufficient shelter during the annual monsoon periods and extreme
storm events defined. The wave conditions at the harbour entrances
and within the harbours have been modelled with the well known hydronumerical
model package MIKE 21®. The average wave conditions along the wharfs
have been analysed considering different reflection properties of the
quay wall. Figure 2 shows a typical result of the modelling for Ambalangoda
harbour, the nearfield modelling and the harbour wave conditions.
The rubble mound breakwaters have been designed based on physical model
studies considering stability and overtopping.
Considering the soil conditions, the costs and availability of construction
material and lifetime of structures (corrosion) a sheet pile quay solution
has been found as most appropriate.
The quay wall alignment was optimised to avoid rock dredging, to balance
dredging and reclamation works and to avoid unfavourable exposure to
the waves.
The works have been tendered through international competitive bidding
process and the award to the lowest bidder has been recommended by
the consultant. The lowest bid was lower than the Engineer's Estimate
and within the project budget.
|